An agile project will be delivered to a client based on a fixed price in cryptocurrency. Due to the volatility of cryptocurrency, both parties have agreed to adjust the scope to the value of the cryptocurrency at the end of every iteration and halt the project when the agreed price is reached. Which approach should be used in this situation?
©
100
An iterative approach starting with the highest value epic.
A predictive approach with short phases.
An incremental approach with a minimum viable product (MVP).
A flow-based approach starting with the smallest stories.
An incremental approach with a minimum viable product (MVP).