Six agile teams working together on a product. When all of the teams integrated at the product level, many integration issues were observed. The overall product release progress declined and the content will not be able to be accomplished. What should the project manager have done differently?
©
100
Performed a scrum of scrum on a regular basis to help the teams remove impediments.
Ensured frequent and continuous integration of work to obtain early feedback and continuous learning.
Formed a quality control team to test all items coming from each team at the end of each iteration.
Conduct an online session on the integration concept to teach the teams.
Performed a scrum of scrum on a regular basis to help the teams remove impediments.