A project manager is conducting agile release planning with their recently acquired team. They are committed to working together to deliver excellent results. The client asks for a product with limited requirements because of a lack of technical knowledge. What should the project manager do to ensure that the client is satisfied with the final product?

©

100

Set the requirements in a signed contract

Engage the client in every iteration

Have the client provide their own technical engineer

Add more features to the final product

Engage the client in every iteration