Score:
0
A vendor has been contracted by a buyer to develop a new device. The vendor insisted that the contract thoroughly captures the device specifications. The buyer does not have clear requirements upfront and, therefore, requested that the vendor develop the device using agile. The vendor delivers as per the contract, but the buyer is not satisfied with the outcome. Which Agile Manifesto's value was most likely not appropriately applied?
©
100
Customer collaboration over contract negotiations
Pair programming over continuous integration
Business people and developers must work together
Individuals and interactions over processes and tools
Customer collaboration over contract negotiations