During a demonstration, the customer provides feedback and requests a new, urgent enhancement due to a regulation change. What should the agile project managedo next'?
©
100
Add the new requirement to the iteration backlog
Discuss the new requirement during the retrospective
Talk about the new requirement during the next iteration planning meeting
Review the new requirement with the team, and ask them to start work on it
Discuss the new requirement during the retrospective