A project manager is working on an agile project in a changing business environment. The project sponsor is worried about benefits realization and asks the project manager to pay attention to changes that can affect the project. Which action should the project manager take to identify changes that may affect the product?

©

100

Stop the iteration as soon as possible in case an external change that makes the product invaluable is identified.

Take action to reprioritize the backlog after every iteration to evaluate if user stories are still valuable to the business.

Implement face-to-face communication between the team and product owner to change the iteration objectives as needed.

Apply a pair programming technique to react to changes immediately, even in the middle of the iteration.

Take action to reprioritize the backlog after every iteration to evaluate if user stories are still valuable to the business.

Join our mailing list an never miss an update!

  • White Instagram Icon
  • White Facebook Icon
  • White Twitter Icon

Thanks for submitting!

© 2035 by The Grid. Powered and secured by Wix

bottom of page