A project manager has been assigned with initiating a large project to deliver complex equipment. Part of the project will be the result of a long research process, but once this is completed, the other part of the project must be incrementally delivered to the customer.Which approach should the project manager choose for this project?
©
100
Agile
Predictive
Waterfall
Hybrid
Agile