Since the beginning of a project, the product owner keeps asking during ceremonies about the budget spent for each product iteration The product owner seems much more interested in the cost rather than the product itself. What should the project manager have done earlier to change the product owner's behavior?
©
100
Worked on a communications management plan with reports of budget spent in each iteration versus planned to avoid these discussions during ceremonies
Worked on a fixed-price contract to switch the product owner's attention to value instead of money
Worked on different approaches of estimating to give confidence of the cost spent in each product increment.
Worked with the product owner to clarify their role in an agile project and the scope of the agile ceremonies
Worked with the product owner to clarify their role in an agile project and the scope of the agile ceremonies