A project team has finished its first iteration out of six. The iteration's delivery performance (velocity) was 50%. During the iteration retrospective, the team realizes that the complexity of the work was underestimated. What should the project manager do?

©

100

Ask the technical manager to help the team with the issue.

Meet with the team to review internal actions to resolve the situation.

Update the issue log and escalate it to the project sponsor.

Ask to replace some team members with more experienced ones.

Meet with the team to review internal actions to resolve the situation.