A project is on its fourth iteration out of six. During iteration planning, a team member informs the project manager that their computer is not working. What should the project manager do next?

©

100

Ask the other team members to step in and do the work.

Facilitate a priority resolution of the issue with the IT department.

Suggest that the team member contact the IT department.

Update the issue log and escalate the problem to the product owner.