A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned to work on the details and estimates as requested by the client. What should the project manager do before sending the information to the client?
©
100
Work with the team to understand their views and add the appropriate dependencies and risks.
Put the tasks with estimates in the backlog and clarify that the project will not need any reserves.
Sequence the tasks with estimates and add standard risk reserves to use for software development.
Analyze the tasks, provide estimates, include a prototype demo, and send to the client directly.
Work with the team to understand their views and add the appropriate dependencies and risks.