During a sprint, one of the team members found an issue. According to the team member and the product owner, the issue has a higher level of importance than the other features of the sprint, but is not a roadblock to completing it. What should the project lead ask the project team do?
©
100
Submit the issue to the change control board (CCB) to evaluate and formally approve a plan to address it.
Avoid the temptation to make any changes and address the issue in the next sprint.
Address this issue only as it has a higher priority than the remaining features of the same sprint.
Follow the sprint plan by delivering the features established for the sprint and prioritize the issue in the backlog.